Portside Pipe Spool Retrofit
Pipe welding — Port of Brisbane
Overview
Portside Logistics had a 72-hour maintenance window to replace six corroded carbon-steel spools on a washdown line. We pre-fabricated every spool in Wacol from laser-verified site measurements, then cut out, fitted, TIG-welded and hydro-tested the lot across two night shifts.
The risk was restart day: any leak would idle the berth. Every root was argon-purged, every weld mapped, and the line held test pressure first attempt — handed back eight hours inside the window.
Scope of work
- Laser measure and off-site spool fabrication
- Purged TIG roots with MIG fill and cap
- Hydro-test, weld maps and QA dossier
- New supports, gaskets and corrosion coating